Penentuan Waktu Baku dengan Stopwatch Time Study untuk Pengukuran Kerja Operator di PT XYZ Lampung Tengah

Penulis

DOI:

https://doi.org/10.33479/jtiumc.v3i2.76

Kata Kunci:

Work productivity, Work measurement, Stopwatch time study, Workload, Standard time

Abstrak

PT XYZ, a company in the agribusiness sector, operates a chick hatching production line that yields hatching eggs as its final product. Currently, the company's production process lacks standardized working hours across various crucial stations – namely, terminal, pullchick, vaccine, and packing stations. This absence of standardized hours poses a significant challenge, impacting labor productivity. Additionally, the work pace remains inconsistent among employees at these stations, resulting in unpredictable monthly fluctuations in hatching egg production, rendering it unstable. To address these challenges, the implementation of the stopwatch time study method becomes imperative. This research aims to ascertain cycle time, normal time, and establish standard working hours across the terminal, vaccine, pullchick, and packing stations. Furthermore, the goal is to standardize the work time specifically at pullchick and packing stations. The objective is to compare these standard times against the current practices to enhance worker productivity effectively. Following the research, notable improvements have been observed. The terminal station has experienced a 1-train increase in output, rising from the prior 18 trains to 19 trains. Similarly, the vaccine station has shown remarkable progress, with an output surge of 6 boxes per hour, escalating from a previous rate of 25 boxes/hour to 31 boxes/hour. These findings underline the positive impact of implementing standardized work times, indicating enhanced productivity and efficiency across these stations within PT XYZ's production process.

Biografi Penulis

Rizqi Wahyudi, Teknik Industri Institut Teknologi Sumatera

Rizqi Wahyudi is a lecturer at Department of Industrial Engineering, Faculty of Technology Production and Industrial, Institut Teknologi Sumatera, South Lampung, Indonesia. Research Interests : Manufacture System, Product Development, Agroindustri and Safety

Andhyka Tyaz Nugraha, Teknik Industri Institut Teknologi Sumatera

Andhyka Tyaz Nugraha is a lecturer and researcher at Department of Industrial Engineering, Faculty of Technology Production and Industrial, Institut Teknologi Sumatera, South Lampung, Indonesia. Research Interests: Agribusiness, Technology Management, Strategic Management, Supply Chain Management, Energy-Economics, Environment-Economics, Applied Econometrics, Sustainable Development, Green Human Resources Management, Structural Equation Modelling, and Macroeconomics.

Referensi

Astuti, S., Lusia, V., & Khairunnisa, A. (2020). Perhitungan Waktu Standart Untuk Menentukan Jumlah Tenaga Kerja dan Kebutuhan Mesin/Alat pada Proses Produksi Reagen Alat/Asat (GPT) FS (IFCC mod) di PT PDL. Jurnal Kalibrasi, 3(2), 1–19.

Aurelia, C., Noya, S., & Oktiarso, T. (2023). Analisis Produktivitas PT Torabika Eka Semesta Menggunakan Metode Objective Matrix dan Fault Tree Analysis. Jurnal Sains dan Aplikasi Keilmuan Teknik Industri (SAKTI), 3(1), 33-48. https://doi.org/10.33479/jtiumc.v3i1.44

Marcelieno, M., & Ekawati, Y. (2021). Perancangan Sistem Pengendalian Kualitas Menggunakan Pendekatan Statistical Process Control di PT X. Jurnal Sains dan Aplikasi Keilmuan Teknik Industri (SAKTI), 1(2), 53-62. https://doi.org/10.33479/jtiumc.v1i2.8

Mulyadi, M. (2011). Penelitian Kuantitatif dan Kualitatif Serta Pemikiran Dasar Menggabungkannya. Jurnal Studi Komunikasi dan Media, 15(1), 127–138. https://doi.org/10.31445/jskm.2011.150106.

Pasaribu, S.A., Wahyudi, R., & Nugraha, A.T. (2023). Penentuan Waktu Baku pada Proses Pembuatan Paving Block Berjenis Bata (Studi Kasus: CV. Karya Mandiri Sejahtera Bandar Lampung). Sistem : Jurnal Ilmu-Ilmu Teknik, 19(2), 12–20. https://doi.org/10.37303/sistem.v19i2.256.

Rully, T., & Rahmawati, N.T. (2015). Perencanaan Pengukuran Kerja dalam Menentukan Waktu Standar dengan Metode Time Study guna Meningkatkan Produktivitas Kerja pada Divisi Pompa Minyak PT Bukaka Teknik Utama Tbk. JIMFE (Jurnal Ilmiah Manajemen Fakultas Ekonomi), 1(1), 12–18. https://doi.org/10.34203/jimfe.v1i1.442.

Setiawan, N., & Putrianto, N.K. (2021). Perancangan Hazard Identification Risk Assessment and Risk Control (HIRARC) dan Implementasi Solusi pada Stasiun Kerja Lubang Kancing PT Bintang Permata Sejati. Jurnal Sains dan Aplikasi Keilmuan Teknik Industri (SAKTI), 1(1), 01-10. https://doi.org/10.33479/jtiumc.v1i1.2

Sulistianingtyas, D.A., & Putrianto, N.K. (2021). Analisis Kerusakan Mesin Batching Plant PT Duta Borneo Abadi Menggunakan Metode Hazard and Operability Study. Jurnal Sains dan Aplikasi Keilmuan Teknik Industri (SAKTI), 1(2), 89-98. https://doi.org/10.33479/jtiumc.v1i2.12

Tarigan, M.I. (2015). Pengukuran Standar Waktu Kerja untuk Menentukan Jumlah Tenaga Kerja Optimal. Wahana Inovasi, 4(1), 26–35.

Utama, D.A., Nugraha, A.T., & Wahyudi, R. (2023) Penentuan Waktu Baku Optimal dan Analisis Beban Kerja Pada Bagian Produksi Udang PCDTO-IQF di PT. Indo American Seafoods. Jurnal Penelitian dan Aplikasi Sistem dan Teknik Industri (PASTI), 17(2), 150–163. https://doi.org/10.22441/pasti.2023.v17i2.002.

Diterbitkan

2023-12-22

Cara Mengutip

Wahyudi, R., Nugraha, A. T. dan Kinasih, A. S. (2023) “Penentuan Waktu Baku dengan Stopwatch Time Study untuk Pengukuran Kerja Operator di PT XYZ Lampung Tengah”, Jurnal Sains dan Aplikasi Keilmuan Teknik Industri (SAKTI), 3(2), hlm. 79–88. doi: 10.33479/jtiumc.v3i2.76.

Terbitan

Bagian

Articles