Analysis of Overall Equipment Effectiveness and Six Big Losses for Performance Improvement

Case Study of the Versant 3100i Printing Machine at CV XYZ

Authors

  • Iqbal Yamin Packaging Printing Industry Technology Study Program, Graphic Engineering and Publishing Department, Politeknik Negeri Jakarta
  • Nurlita Pratiwi Suharto Packaging Printing Industry Technology Study Program, Graphic Engineering and Publishing Department, Politeknik Negeri Jakarta
  • Tegar Bayu Satriaji Packaging Printing Industry Technology Study Program, Graphic Engineering and Publishing Department, Politeknik Negeri Jakarta
  • Valeri Vela Sinur Packaging Printing Industry Technology Study Program, Graphic Engineering and Publishing Department, Politeknik Negeri Jakarta
  • Zulkarnain Zulkarnain Packaging Printing Industry Technology Study Program, Graphic Engineering and Publishing Department, Politeknik Negeri Jakarta

DOI:

https://doi.org/10.33479/sakti.v5i02.143

Keywords:

fishbone diagram, overall equipment effectiveness, six big losses, total productive maintenance, machine performance

Abstract

This study examines machine performance inefficiencies in a digital printing production system by applying the Overall Equipment Effectiveness (OEE) method to the Versant 3100i digital printing machine at CV XYZ. The objective of this research is to evaluate machine effectiveness, identify dominant sources of production losses, and analyze their root causes to support operational performance improvement. An integrated analytical approach is employed by combining OEE measurement, Six Big Losses analysis, and Fishbone Diagram techniques to systematically diagnose machine performance issues. The results show that the average OEE value of the Versant 3100i machine is 82.92%, which remains below the international benchmark of 85%, indicating that machine performance has not yet reached an optimal level. Analysis of the Six Big Losses reveals that Reduced Speed is the most significant contributor to performance loss, accounting for 36.24% of total losses. Further analysis using a Fishbone Diagram indicates that Reduced Speed is mainly caused by human-related factors and the absence of standardized Standard Operating Procedures (SOPs). Based on these findings, targeted improvement strategies are proposed, including structured operator training, the implementation of standardized operating procedures, and the strengthening of quality control mechanisms. This study demonstrates that the integrated use of OEE, Six Big Losses, and Fishbone Diagram analysis is effective in identifying priority improvement areas and formulating practical improvement strategies. The proposed approach can be applied by manufacturing companies to enhance machine effectiveness and operational efficiency, particularly in digital printing production environments.

Author Biographies

Tegar Bayu Satriaji, Packaging Printing Industry Technology Study Program, Graphic Engineering and Publishing Department, Politeknik Negeri Jakarta

Packaging Printing Industry Technology Study Program, Graphic Engineering and Publishing Department,

Valeri Vela Sinur, Packaging Printing Industry Technology Study Program, Graphic Engineering and Publishing Department, Politeknik Negeri Jakarta

Packaging Printing Industry Technology Study Program, Graphic Engineering and Publishing Department

References

Adha, M. A., Supriyanto, A., & Timan, A. (2019). Strategi Peningkatan Mutu Lulusan Madrasah Menggunakan Diagram Fishbone. Jurnal Keilmuan Manajemen Pendidikan, 5(01), 11–22.

Ahadya Silka Fajaranie, & Khairi, A. N. (2022). Pengamatan Cacat Kemasan Pada Produk Mie Kering Menggunakan Peta Kendali Dan Diagram Fishbone Di Perusahaan Produsen Mie Kering Semarang, Jawa Tengah. Jurnal Pengolahan Pangan, 7(1), 7–13. https://doi.org/10.31970/pangan.v7i1.69

Akhmad Ghiffary Budianto. (2021). Analisis Penyebab Ketidaksesuaian Produksi Flute Pada Ruang Handatsuke Dengan Pendekatan Fishbone Diagram, Piramida Kualitas Dan Fmea. Journal of Industrial Engineering and Operation Management , 4(1), 17–23.

Amelia, C., Industri, T., Kemasan, C., Grafika, T., & Jakarta, P. N. (2024). Analisis Efektivitas Mesin Cetak Rotogravure Dengan Metode Overall Equipment Effectiveness ( OEE ) dan Six Big Losses. 4(1), 133–141.

Anrinda, M., Sianto, M. E., & Mulyana, I. J. (2021). Analisis Perhitungan Overall Equipment Effectiveness (Oee) Pada Mesin Offset Cd6 Di Industri Offset Printing. Presiding Seminar Nasional Riset Dan Teknologi Terapan (Ritektra), 1.

Dewanti, G. K., & Putra, M. F. (2019). Perhitungan Nilai Overall Equipment Efectiveness (OEE) Mesin Printing Amplas Kertas. Jurnal Optimasi Teknik Industri (JOTI), 1(2), 1. https://doi.org/10.30998/joti.v1i2.4175

Dwijayanto, M. R., & Irjayanti, M. (2026). Analysis of Lean Manufacturing Efficiency and Effectiveness Using a Digital Kanban System at. 5(1), 52–65.

Farquhar, J., Michels, N., & Robson, J. (2020). Triangulation in industrial qualitative case study research : Widening the scope. Industrial Marketing Management, November 2019, 1–11. https://doi.org/10.1016/j.indmarman.2020.02.001

Indriawanti, V., & Bernik, M. (2020). Analisis Penerapan Total Productive Maintanance (TPM) dengan Menggunakan Metode Overall Equipment Effectiveness (OEE) pada Mesin Printing. Jurnal Teknik Industri, 10(1), 42–52. https://doi.org/10.25105/jti.v10i1.8388

Mahardika, sakti, bimo, & Noubnome, V. (2024). Analisis Peningkatan Produktivitas Kerja Mesin CrimpingMenggunakan Metode Total Productive MaintenanceDi CV XYZ. Journal Of Social Science Research, 4(1), 11838–11850.

Mario, R., Leke, S., & Saifuddin, J. A. (2024). Proposed Total Productive Maintenance ( TPM ) Implementation to Increase Heading Machine Effectiveness Using Overall Equipment Effectiveness ( OEE ) Method on PT . XYZ. 5(2), 359–369. https://doi.org/10.22441/ijiem.v5i2.23832

Pratitis, A. C. W., & Maryanty, Y. (2024). Evaluasi Tpm (Total Productive Maintenance) Dan Penerapan Am (Autonomous Maintenance) Pada Produksi Susu Kental Manis Di Pabrik Dairy. DISTILAT: Jurnal Teknologi Separasi, 10(1), 245–255. https://doi.org/10.33795/distilat.v10i1.4908

Ramadhani, A. G., Azizah, D. Z., Nugraha, F., & Fauzi, M. (2022). Analisa Penerapan TPM (Total Productive Maintenance) Dan OEE (Overall Equipment Effectiveness) Pada Mesin Auto Cutting Di PT XYZ. Jurnal Ilmiah Teknik Dan Manajemen Industri, 2(1).

Wardani, I. K., Tatas, F., Atmaji, D., & Alhilman, J. (2021). Pengukuran dan analisa efektivitas mesin pencetak paving menggunakan metode overall equipment effectiveness ( OEE ). 7(1).

Wiyatno, T. N., Sutriyanto, D., & Edy, S. (2024). Analysis of Machine Performance with Calculations Overall Equipment Effetiveness on Packing Line Automation Machine. 3(9), 1959–1980.

Downloads

Published

23-12-2025

How to Cite

Yamin, I., Suharto, N. P., Satriaji, T. B., Sinur, V. V. . and Zulkarnain, Z. (2025) “Analysis of Overall Equipment Effectiveness and Six Big Losses for Performance Improvement : Case Study of the Versant 3100i Printing Machine at CV XYZ”, Jurnal Sains dan Aplikasi Keilmuan Teknik Industri (SAKTI), 5(02), pp. 97–110. doi: 10.33479/sakti.v5i02.143.